D
Daisy
Hi,
I have created a project and have assigned some task to the
resources.Through PSI i want to access the no. of hours the resource had to
work in the project. I didn't find any table from database where I can get
those hours.So that the total effort given by the resource can be
calculated.How can I get the hours of work assigned to the resource.Please
help
I have created a project and have assigned some task to the
resources.Through PSI i want to access the no. of hours the resource had to
work in the project. I didn't find any table from database where I can get
those hours.So that the total effort given by the resource can be
calculated.How can I get the hours of work assigned to the resource.Please
help