I tried setting the baseline and without baseline
:
Did you set a baseline yet?
-Jack Dahlgren
Thanks Jim,
But I have tried and nothing, the values are in Excel in zero. I
only have
the plan, I do no have the progress yet.
:
Project 2003: In the analyze Time Phased Data in Excel, you will
want to
set
the status date far into the future. Then export the desired
fields.
Traditionally, BCWS, BCWP (Earned Value or EV) and ACWP (Acutal
Cost or
AC).
Graphcis are then created in Excel from the export.
Project2007: This is a visual report already supplied.
Reports/Visual
Reports... it poduces a nice chart in Excel for you.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project
:
How can I get the s plan curve from Project?
I am trying using Analyze Timescaled data but I do not what
field I
have to
choose.