T
ted10s
I want the taskpad to show only those tasks that have a start date today or
earlier and have not been checked off as completed. This used to work until
I had to have my hard drive wiped and formatted, and Office re-installed.
Now taskpad shows only a few of the tasks, even though I can see the other
tasks when I go to the Tasks window. Also, previously when I checked off a
task, it stayed on the taskpad but moved to the bottom and had a line through
it. Now it disappears from the taskpad when completed. I prefer the former
functionality. I have tried umpteen variations on task and taskpad settings,
but nothing restores the earlier view. Thanks.
earlier and have not been checked off as completed. This used to work until
I had to have my hard drive wiped and formatted, and Office re-installed.
Now taskpad shows only a few of the tasks, even though I can see the other
tasks when I go to the Tasks window. Also, previously when I checked off a
task, it stayed on the taskpad but moved to the bottom and had a line through
it. Now it disappears from the taskpad when completed. I prefer the former
functionality. I have tried umpteen variations on task and taskpad settings,
but nothing restores the earlier view. Thanks.