How can I highlight overdue tasks in MS Project

N

Nicks

Is there any easy way to highlight (e.g. turn them red) any tasks that are
past their due date and not 100% complete. We've got quite a big project
plan and it would be great just to scan it and be able to easily pick out
those that are overdue...

Thanks,
Nic
 
J

JulieS

Hello Nic,

You'll find the Status field or Status Indicator field shows that
information and is as easy as adding the field(s) to a table.

It will not turn tasks red (that would require some VBA programming I
believe).

See help on the Status field or Status Indicator and let us know if you
have any additional questions.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
J

John Sitka

Additionaly, if you want to focus on fewer than all the tasks place deadlines on milestones
or tasks that represent landmarks in your business idea.
A red triangle will appear in the Information column whenever a task crosses it's deadline.
 