How can I indicate resource usage on the gantt chart?

B

benn

I need to assign two work resources to the same workorder. How can I
indicate one of the resources will be needed for 2hrs and the other for 4hrs
on the same workorder task? Can this be shown on the gantt chart as %
utilization? (50% would equal 4hrs and 25% would equal 2hrs)
 