How can I let users update the start and finish dates?

B

bholze

How do I enable the start and finish dates to be editable from the Web
Project Server so the users on the team can enter the dates they start and
stop the tasks?
 
E

Earl Lewis

I think you may to change your paradigm on this a little bit. Users actually do this automatically by entering time/work against a task. The first time any work is entered by any single resource against a task it triggers project server to populate the Actual Start date field. In like fashion, when resources (all resources assigned to the task) indicates a task is complete (Remaining Work is zero) the Actual Finish is populated.

Oh, and if you didn't get it from the above comments, any one task is NOT finished until all the resources that are assigned to the task have indicated that there is zero work remaining for that specific task - so don't expect tasks so show actual completion unless that is true. Actual Finish will show NA until all resources report zero work remaining.

If you're talking about the planned start and finish dates - these are something only the project manager can change, through Project Professional. These fields are referred to as Start and Finish.

If you use baselines - which you should, so you can see how your plan changes over time - this all becomes a little more complicated. When the baseline is saved the original Start and Finish dates are copied into Baseline Start and Baseline Finish. Then those dates are used for planned start and finish from then on - unless of course you remove the baseline.

Hope that helps.

Earl
How do I enable the start and finish dates to be editable from the Web
Project Server so the users on the team can enter the dates they start and
stop the tasks?
 
G

Gary L. Chefetz \(MVP\)

Earl:

When you say-

"Users actually do this automatically by entering time/work against a task.
The first time any work is entered by any single resource against a task it
triggers project server to populate the Actual Start date field."

You should be aware that this is only true if hours/per day is used as the
tracking method, and the task type is not fixed-duration.

Otherwise, the Project Manager can push Actual Start and Actual Finish to
the timesheet by going to Customize > Published fields in project, after the
PWA administrator modifies the timesheet view to contain these fields.
 
E

Earl Lewis

Gary,

Nice! I never realized that was possible. Good tidbit of info. Thank you for the clarification.

Earl
Earl:

When you say-

"Users actually do this automatically by entering time/work against a task.
The first time any work is entered by any single resource against a task it
triggers project server to populate the Actual Start date field."

You should be aware that this is only true if hours/per day is used as the
tracking method, and the task type is not fixed-duration.

Otherwise, the Project Manager can push Actual Start and Actual Finish to
the timesheet by going to Customize > Published fields in project, after the
PWA administrator modifies the timesheet view to contain these fields.
 
G

Gary L. Chefetz \(MVP\)

Earl:

Your PM practice is probably a bit more mature than most. Actual start and
finish can only be captured if you do it this way when using %complete
tracking method. Otherwise, all the planned dates are assumed to be actual,
no matter what date the status is applied. Another argument for effort-based
planning.

--

Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com

-
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top