How can I schedule with optimistic and pessimistic date?

J

JustMe

I want to create a project schedule in which some tasks with different
levels of confidence are illustrated with optimistic and pessmistic
dates. My goal is to compile a schedule with milestone in which I can
show the best and worst possible scenario.

Anyone can give me some pointer how to do it in Microsoft Project?

Thanks.

Frank
 
H

Helge Svee

If you link your activiies in a network you automaticly get a early-plan and
a late-plan.

To display these plans you just have to make bars who shows early
start/early finish and late start/late finish

JustMe skrev:
 
M

Mike Glen

Hi Frank,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #29 - PERT, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 