How can I see Baseline 2

M

Mona K Gupta

How can I see the baseline #2 that I created? When I look
at the plan, there is still no trace of that particular
baseline.
 
J

Jack D.

Mona said:
How can I see the baseline #2 that I created? When I look
at the plan, there is still no trace of that particular
baseline.

Go to format menu / barstyles and create a style(s) which go from
Baseline2Start to Baseline2Finish

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP
email: J -at- eM Vee Pee S dot COM


+++++++++++++++++++
 
M

Mike Glen

Hi Mona,

Welcome to this Microsoft Project newsgroup :)

Please see FAQ Item: 14. Viewing Multiple Baselines

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
G

Guest

-----Original Message-----
How can I see the baseline #2 that I created? When I look
at the plan, there is still no trace of that particular
baseline.
.

In a Gannt-view; choose Format --> Bar Styles. Create a
new instance by clicking Insert. Choose color and style
and then enter Baseline2 Start under the heading From and
Baseline2 finish under the heading To. Depending if you
want to display the baseline for tasks or summary tasks
choose the appropriate type under Show For ... Tasks.
Good luck!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top