A
Atilla Otaner
Hi,
I have a task for which several resources are assigned. Some resources has
completed its
work but some still has some work to do. I would like to display only the
resources that
still has work to do in the Bars of the Gannt Chart. I have tried with
showing the reources
from Complete Through to Finish, but that does not change the resources only
the Bar Style?
Any help on this?
PS One task per resource would solve the problem, since I could filter the
completed once out,
but that is not acceptable for my case...
Thanks,
/// Atilla
I have a task for which several resources are assigned. Some resources has
completed its
work but some still has some work to do. I would like to display only the
resources that
still has work to do in the Bars of the Gannt Chart. I have tried with
showing the reources
from Complete Through to Finish, but that does not change the resources only
the Bar Style?
Any help on this?
PS One task per resource would solve the problem, since I could filter the
completed once out,
but that is not acceptable for my case...
Thanks,
/// Atilla