DerekM --
The columns used in PERT analysis are simply custom fields. For example,
Optimistic Duration is really the Duration1 field, Optimistic Start is the
Start1 field, and Optimistic Finish is the Finish1 field. To view these
fields in PWA, such as in a detailed Project view, your Project Server
administrator would need to create one or more custom PWA views and would
need to add the fields using their real names. You would need to republish
the project using Collaborate - Publish - Project Plan to "push" the PERT
fields to PWA. Do know, however, that you cannot see the Optimistic,
Expected, and Pessmistic Gantt Charts in PWA. Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"