A
Al
I have an independent task that was scheduled to finish on 8/25/09,
constraint Type is "As soon as possible". The task was finished ahead to
time, today. However, MS Project is showing that the task is finished on
8/25/09 even though today is 8/5/09; we are not at this date yet. Is there a
way to make Project reflect the original deadline and that the project was
finished ahead of time?
constraint Type is "As soon as possible". The task was finished ahead to
time, today. However, MS Project is showing that the task is finished on
8/25/09 even though today is 8/5/09; we are not at this date yet. Is there a
way to make Project reflect the original deadline and that the project was
finished ahead of time?