Is there any way to have the team members update the actual start and finish
date along with their work using Project Web Acess (PWA)??
The problem I'm having is due to the fact that if a task takes longer than
anticipated the following tasks are not shifted to reflect the delay. Rather,
the following tasks still occur on the sceduled date. If the memebers can
update the actual start date using PWA this overlap can be avoided.
date along with their work using Project Web Acess (PWA)??
The problem I'm having is due to the fact that if a task takes longer than
anticipated the following tasks are not shifted to reflect the delay. Rather,
the following tasks still occur on the sceduled date. If the memebers can
update the actual start date using PWA this overlap can be avoided.