P
Phil
I'm trying to take the costs associated with a number of activities (approx
6000), roll them up to a summary level (approx 1200) and produce a cash flow
using MS Project.
Is there any way to create either a linear spread of the $$ against the
schedule. Preferably, I would spread the costs on specific criteria against
activities with similar traits, but would accept a linear spread of costs
against the schedule.
Thanks,
6000), roll them up to a summary level (approx 1200) and produce a cash flow
using MS Project.
Is there any way to create either a linear spread of the $$ against the
schedule. Preferably, I would spread the costs on specific criteria against
activities with similar traits, but would accept a linear spread of costs
against the schedule.
Thanks,