I
Imran Admin
currently The resource should change the "Remaining Time" field in their My
Tasks view for the task and submit that as an update.
well employee will never change the remaining time and will show as
everthing is on time even if task was 1 hour starting at 10am and finishing
at 11am, employee finished at 11:30 he will simply update progress to 100%
and submit and what i will know is it completed in time where as it was not...
how can i automatically know that it was suppose to finish and get update as
finished and what was original time schedule for minus time reported with
update = actual time task took...
also how can person start the task there must be a button to press that i am
beginning to work on this task which is scheduled at 10 am
Tasks view for the task and submit that as an update.
well employee will never change the remaining time and will show as
everthing is on time even if task was 1 hour starting at 10am and finishing
at 11am, employee finished at 11:30 he will simply update progress to 100%
and submit and what i will know is it completed in time where as it was not...
how can i automatically know that it was suppose to finish and get update as
finished and what was original time schedule for minus time reported with
update = actual time task took...
also how can person start the task there must be a button to press that i am
beginning to work on this task which is scheduled at 10 am