In MSP 2002 there was a "hide" option so once resources completed work on a
task they could get it off of thier task list. This option seems to not exist
in MSP 2007.
I ran some experiments today using the 'delete' option but if there are
actuals tied to the task they can not be deleted from the project and
therefore can not be deleted from the 'my tasks' page.
How can I help my resources 'Hide' or 'remove' tasks that have been completed?
Second question - In the 'my tasks' page can the projects summary tasks be
shown in conjunction with the tasks?
task they could get it off of thier task list. This option seems to not exist
in MSP 2007.
I ran some experiments today using the 'delete' option but if there are
actuals tied to the task they can not be deleted from the project and
therefore can not be deleted from the 'my tasks' page.
How can I help my resources 'Hide' or 'remove' tasks that have been completed?
Second question - In the 'my tasks' page can the projects summary tasks be
shown in conjunction with the tasks?