Å
åŠæ–°ä¸æ—§
Hi, in case of team members cerate a new task under an existing project, they
can only specify "Start Date", "Finish Date" or "Total work". Finish date and
total work always impact eachother, ie. "total work = finish date - start
date" and vice versa. This creation works with when new tasks are Fixed
Duration.
Is it possible that resources are able to create a new task with fixed unit
attribute? i.e. "start date" "finish date" and "Total work" could be entered
independantly on <New Task> page so that a task may last 10 days long but
only 8 hours total work?
Thanks in advance,
JJin
can only specify "Start Date", "Finish Date" or "Total work". Finish date and
total work always impact eachother, ie. "total work = finish date - start
date" and vice versa. This creation works with when new tasks are Fixed
Duration.
Is it possible that resources are able to create a new task with fixed unit
attribute? i.e. "start date" "finish date" and "Total work" could be entered
independantly on <New Task> page so that a task may last 10 days long but
only 8 hours total work?
Thanks in advance,
JJin