How can team member make "Act duration" less then planned duration

S

Shurick

Resource can increase duration of task. Can he decrease it?

Project 2003.
PWA, PWA add-in
 
G

Gérard Ducouret

Shurick,

The resource can decrease the Remaining work in his/her timesheet (PWA :
View my tasks)

Gérard Ducouret
 
D

Dale Howard [MVP]

PWA --

Yes. When the Remaining Work is greater than 0 hour for a task that was
completed early, the team member can decrease the Duration of the task by
setting the Remaining Work to 0 hours. Hope this helps.
 
S

Shurick

Thank you, Dale Howard and Gerard Ducouret!

Dale Howard said:
PWA --

Yes. When the Remaining Work is greater than 0 hour for a task that was
completed early, the team member can decrease the Duration of the task by
setting the Remaining Work to 0 hours. Hope this helps.
 