What I mean is I update Enterprise users calendars with vacation, holidays,
etc in MS Professional 2003 and I want the users to see that information in
PWA.
 
G

Gary L. Chefetz \(MVP\)

Derek

There is no way to change resource calendar information through PWA. You can
view it rather obtusely if you have access to resource information and view
resource availability and can guess which blocks of unavailability represent
vacations. We've done some custom work to add this type of functionality.

--

Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com

For Project Server FAQs visit
http://www.projectserverexperts.com

For Project FAQs visit
http://www.mvps.org/project

-
 