What I mean is I update Enterprise users calendars with vacation, holidays,
etc in MS Professional 2003 and I want the users to see that information in
PWA.
There is no way to change resource calendar information through PWA. You can
view it rather obtusely if you have access to resource information and view
resource availability and can guess which blocks of unavailability represent
vacations. We've done some custom work to add this type of functionality.
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.