T
tbbg
We have an upcoming event that we're tracking in MS Project that will require
many volunteers in multiple positions. However, at this early stage we only
know that certain tasks will need a certain number of volunteers (i.e. "Task
41 - Set up volunteer check-in table" will need 2-3 volunteers) but we don't
know any names yet.
I'm afraid that if I add "Volunteer 1", "Volunteer 2", etc as work resources
to the Resource list and assign these resources to tasks, it will create a
nightmare later when we update the volunteer resources with actual names.
I've also played around with assigning volunteers as material resources
instead (using "Volunteer(s)" as the material label and adding the actual
volunteers later as work resources), but it hasn't been an entirely
satisfactory solution.
Any suggestions would be appreciated - thanks!
many volunteers in multiple positions. However, at this early stage we only
know that certain tasks will need a certain number of volunteers (i.e. "Task
41 - Set up volunteer check-in table" will need 2-3 volunteers) but we don't
know any names yet.
I'm afraid that if I add "Volunteer 1", "Volunteer 2", etc as work resources
to the Resource list and assign these resources to tasks, it will create a
nightmare later when we update the volunteer resources with actual names.
I've also played around with assigning volunteers as material resources
instead (using "Volunteer(s)" as the material label and adding the actual
volunteers later as work resources), but it hasn't been an entirely
satisfactory solution.
Any suggestions would be appreciated - thanks!