How can you display remaining work in hours (not days) in timeshee

A

Avi

Is there a way to display Remaining Work in hours opposed to days (default)
in My Timesheets? We want to use this to communicate remaining work on task
to PMs in our Timesheet Tied Mode installation.
 
M

Mike Glen

Hi Avi,

This sounds like you're using Project Server. Try posting on the
microsoft.public.project.server newsgroup (forum). Please see FAQ Item: 24.
Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top