H
Hung
Hi,
We started using projects with a list of resources in enterprise resource
pool, with Cost perhour set initially to 100$/hour.
After few months of working, we saw that it would be better to change it to
$1/hour so that the number can reflect immediately the number of hours.
How this change today affects the existing value of ACWP and BCWP/BCWS which
got some values already during the last few months?
I saw that these values started to get confused values.
Can we do something to ask MSP to recalculate the time-based values so that
everything could be as if it were 1$/h since the beginning?
Thanks
We started using projects with a list of resources in enterprise resource
pool, with Cost perhour set initially to 100$/hour.
After few months of working, we saw that it would be better to change it to
$1/hour so that the number can reflect immediately the number of hours.
How this change today affects the existing value of ACWP and BCWP/BCWS which
got some values already during the last few months?
I saw that these values started to get confused values.
Can we do something to ask MSP to recalculate the time-based values so that
everything could be as if it were 1$/h since the beginning?
Thanks