L
LizJ
I am running Project Server and Project Professional 2003. My scenario is
this. I have several resources, each of whom have a list of tasks to
complete that I would now like to add to Project to help me to understand
when these tasks are likely to occur on the basis of the amount of work they
are likely to take and the resources required etc.
I have two questions
1. My resources will not always be working on Project Tasks (about 20% of
their time will be spent on additional things - admin etc.) To get as
realistic as possible an indication of the duration of a task, and whether a
resource is overallocated, is it best to allocate a resource as available
only 80% of the time in the enterprise, or in each project? If I do this in
each project, will Project tell me when the resource is overallocated across
multiple project tasks, and will I have to manually adjust the %age
allocation on the basis that a person working for 4 hours a day on a task is
working at 40% rather than 50%.
2. When resources update their actual work, they may have worked on a task
for the full 8 hours that they are in the office, (they did nothing else that
day) if I set them to 80% available surely this will show the resource as
having done too much work that day (i.e. been in the office too long).
We also have a flexi-time system, so it is conceivable that a resource may
actually work on project tasks for longer than the 8 hours they are meant to
be in the office e.g. 9 hours. I need to be able to identify what is
flexi-time, and what is simply working hours, in order that time can be
credited back to the individual concerned. Any suggestions as to how best to
represent this?
For information I have decided against using administrative projects and
tasks and rather to use non-working time for scheduling in order that other
tasks are re-scheduled on this basis - is this the best scenario?
My apologies for the length of this post. Any suggestions would be
appreciated. Thanks
this. I have several resources, each of whom have a list of tasks to
complete that I would now like to add to Project to help me to understand
when these tasks are likely to occur on the basis of the amount of work they
are likely to take and the resources required etc.
I have two questions
1. My resources will not always be working on Project Tasks (about 20% of
their time will be spent on additional things - admin etc.) To get as
realistic as possible an indication of the duration of a task, and whether a
resource is overallocated, is it best to allocate a resource as available
only 80% of the time in the enterprise, or in each project? If I do this in
each project, will Project tell me when the resource is overallocated across
multiple project tasks, and will I have to manually adjust the %age
allocation on the basis that a person working for 4 hours a day on a task is
working at 40% rather than 50%.
2. When resources update their actual work, they may have worked on a task
for the full 8 hours that they are in the office, (they did nothing else that
day) if I set them to 80% available surely this will show the resource as
having done too much work that day (i.e. been in the office too long).
We also have a flexi-time system, so it is conceivable that a resource may
actually work on project tasks for longer than the 8 hours they are meant to
be in the office e.g. 9 hours. I need to be able to identify what is
flexi-time, and what is simply working hours, in order that time can be
credited back to the individual concerned. Any suggestions as to how best to
represent this?
For information I have decided against using administrative projects and
tasks and rather to use non-working time for scheduling in order that other
tasks are re-scheduled on this basis - is this the best scenario?
My apologies for the length of this post. Any suggestions would be
appreciated. Thanks