We are trying to show the amounts of money that we have actually received on
each of our projects as well as the output of resources. Is there a way to
account for monies received in MS Project?
 
J

Jan De Messemaeker

Hi,

You can but you have to invent all from scratch
You can enter them in one of the custom Cost fireds (like Cost1, Cost2...)
Then you can use yest another custom cost field to enter a formula to
calculate profit or loss or comparison to a baseline...
HTH
 