How do I add a comment onto a specific task in Project?

M

madsmom

I need to be able to add a specific comment onto a task so it show just like
it does in Excel. Notes in the task information box is not good enough.
 
J

Jim Aksel

Let me add to Andrews post-- When you are done creating the Text Box on the
Gantt chart, right click on it and select Properties. From there you can
force the box to attach itself to a specific date or task.

It is not possible to have a "Hover over me comment" like excel on the left
side of the Gantt. You'll have to use the Notes filed on the left side.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 