How do I add additional heads to a task part way through duration.

T

TB

MSP 2003 - trying to add an additional resource to a task from a specific
date which is part way through the overall task duration
 
J

Jack Dahlgren

Switch to the task usage or resource usage view. This will allow you to enter
the assignment and edit it to take place when you want.

-Jack Dahlgren
 