How can i change a non working day to working day in MS Project -2007.
I want to change saturday a full working day for throught the project
duration.
I Know how to change in MSp -2003 but i can't get in 2007 version.
 
J

JulieS

Hello Neelima,

To change all Saturdays to working days:

Tools > Change Working Time.
Click the "Work Weeks" tab.
Click the Details... button to show the Details dialog box.
In the Select day(s): list, click on Saturday.
Click in the button "Set day(s) to these specific working times:" and
enter the times in the From and To section as needed.
Click OK to close the Details dialog box and return to the Change
Working Time dialog box.
Click OK to close the Change Working Time dialog box.


I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top