Hi there!
I assigned a resource to a task. The task has started and work
underway (like 50% complete). Now I want a new resource to take over
the task from the old one but the new resource has a different rate
from old. If I just add the resource, MSP divides the work. If I
remove the old resources and add the new one, the work done by the old
resource is ignored and the cost skewed.
any ideas?