Hi there I am hoping someone can help me, I am experiencing a problem M
projects 2007. I want to assign multiple calenders to my project ie,
want have standerd calender and a 24 hr calender assigned to the to sam
project, where I have about half my activities on a standerd calende
and the the other half on a 24 hr calender.
When I assign my the 24 hr calender to my certain activities, i
assigns the 24 hr calender but the duration still remainds 5 days wher
it should change to about 2 days with a 24 hr calender assigned to it
Can someone help me please, thank
projects 2007. I want to assign multiple calenders to my project ie,
want have standerd calender and a 24 hr calender assigned to the to sam
project, where I have about half my activities on a standerd calende
and the the other half on a 24 hr calender.
When I assign my the 24 hr calender to my certain activities, i
assigns the 24 hr calender but the duration still remainds 5 days wher
it should change to about 2 days with a 24 hr calender assigned to it
Can someone help me please, thank