Larry ER
I have been tasked to create a general form that will contan multiple
projects (i.e. a schedule for all in house orders for multiple end users).
This project file needs to be back driven from a shippng date of the multiple
projects. Our ship date is directly proceeded by 8 week period for parts
procurement and manufacturing. That time frame is proceeded by electrical and
mechanical engineering time frames which will run concurrently, but may not
require the same time frame. The engineering time frame is directly proceeded
by the application engineering time.
To add a twist to this, the form is also going to be used for scheduling the
equipment installation and start up following the ship date. this form could
have as many as 20 projects that are not linked and the form needs to accept
new projects that will be inserted between existing projects in this file, as
we get projects in that may ship prior to ones already documented.
Any help would be greatly appreciated. Thanks.
projects (i.e. a schedule for all in house orders for multiple end users).
This project file needs to be back driven from a shippng date of the multiple
projects. Our ship date is directly proceeded by 8 week period for parts
procurement and manufacturing. That time frame is proceeded by electrical and
mechanical engineering time frames which will run concurrently, but may not
require the same time frame. The engineering time frame is directly proceeded
by the application engineering time.
To add a twist to this, the form is also going to be used for scheduling the
equipment installation and start up following the ship date. this form could
have as many as 20 projects that are not linked and the form needs to accept
new projects that will be inserted between existing projects in this file, as
we get projects in that may ship prior to ones already documented.
Any help would be greatly appreciated. Thanks.