D
Dennis Meyer
I need to know how long it takes to deliver a task... not how many working
hours are involved (duration as calcualted by MS Project), but what is the
absolute difference between the start date/time and end date/time? I can
manually count the number of days and hours between the start date and end
date, but...
For example, I start a task on Tues 7/5/05 8:00AM and finish it on Sun
7/17/05 7:39 PM. The time it took to deliver the task was 12 days and almost
12 hours. Project calculates duration as 15.71 days, because some resources
work different shifts (8hrs, 12hrs, 10hrs). The duration as calculated is
useful, but not exactly what I need.
Anyone out there able to help?
Thanks.
hours are involved (duration as calcualted by MS Project), but what is the
absolute difference between the start date/time and end date/time? I can
manually count the number of days and hours between the start date and end
date, but...
For example, I start a task on Tues 7/5/05 8:00AM and finish it on Sun
7/17/05 7:39 PM. The time it took to deliver the task was 12 days and almost
12 hours. Project calculates duration as 15.71 days, because some resources
work different shifts (8hrs, 12hrs, 10hrs). The duration as calculated is
useful, but not exactly what I need.
Anyone out there able to help?
Thanks.