how do I change a constraint without effecting other tasks?

R

Rod Gill

You didn't say what constraint in what version of project so let's assume
Task constraint in any version. Changing the constraint won't recalculate
anything unless you change a value (Units, Work or Duration) as well. Then
what gets changed is exactly the same as doing the same thing manually. So,
test manually then implement in VBA.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 