You didn't say what constraint in what version of project so let's assume
Task constraint in any version. Changing the constraint won't recalculate
anything unless you change a value (Units, Work or Duration) as well. Then
what gets changed is exactly the same as doing the same thing manually. So,
test manually then implement in VBA.
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com