H
hmhart
I need to change the assignment owner of a bunch of tasks from one resource
to another, but the assignment owner column is grayed out.
The assignments in question are local resources.
The previous owner is a resource ID being removed from the system, but is
still active until we can remove everything.
The to-be owner is the project manager.
What happened:
1. If I add an "assignment owner" column to a task view, those specific to
the local resources are grayed out and cannot be changed.
2. If I open the task information --> resources tab, the drop down arrow is
grayed out and the entry in the line above the resources. So no change can
be made there.
3. I made one of the local resources an enterprise resource (all of these
should have been added as enterprise). I used the "replace" function to
replace the local with the enterprise resource by the same name.
4. Same problem with the assignment owner column in a task view.
5. Different in the task information --> resources tab: I would click the
dropdown for the name, then the "resource owner" field would blank out. But
I could not enter anything in that field. At this point, I did not save the
task changes, nor did I save the project for fear of ruining it. (It belongs
to a project manager.)
I do have full access to the Project Server databases and can perform
repairs at that level if that is the only place. But with the extreme
interconnection of everything, I won't do that on my own.
Any ideas would be appreciated.
Thanks,
Mac Hart
Software Engineer
(e-mail address removed)
to another, but the assignment owner column is grayed out.
The assignments in question are local resources.
The previous owner is a resource ID being removed from the system, but is
still active until we can remove everything.
The to-be owner is the project manager.
What happened:
1. If I add an "assignment owner" column to a task view, those specific to
the local resources are grayed out and cannot be changed.
2. If I open the task information --> resources tab, the drop down arrow is
grayed out and the entry in the line above the resources. So no change can
be made there.
3. I made one of the local resources an enterprise resource (all of these
should have been added as enterprise). I used the "replace" function to
replace the local with the enterprise resource by the same name.
4. Same problem with the assignment owner column in a task view.
5. Different in the task information --> resources tab: I would click the
dropdown for the name, then the "resource owner" field would blank out. But
I could not enter anything in that field. At this point, I did not save the
task changes, nor did I save the project for fear of ruining it. (It belongs
to a project manager.)
I do have full access to the Project Server databases and can perform
repairs at that level if that is the only place. But with the extreme
interconnection of everything, I won't do that on my own.
Any ideas would be appreciated.
Thanks,
Mac Hart
Software Engineer
(e-mail address removed)