How do I change the AM/PM time to 0001 - 2400 time.

A

Andrew

I am seeking to set up a Project using non AM/PM time ie use 2400 hrs instead.

Can this be done?
 
R

Rod Gill

Hi,

Yes. Project uses whatever your Regional setting is in the Control Panel.
So, go to the control panel and reset your default time format. No need to
even close Project usually either, it just changes.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 