How do I change the default 60 day task update history in Project

M

matric

How do I change the default setting for the number of days that are available
in MS Project task update history. The default is 60 days and the link below
says that it can be set by the Project Server Administrator.

http://office.microsoft.com/en-us/assistance/HA011713101033.aspx

“Viewing Task Change History

You can view a history of all task changes that were processed within the
previous 60 days. This history is for review purposes only; it cannot be
modified. This enables you to review the history of updates made for all
projects and resources. The update archive displays the updated tasks in a
similar format to the Update task changes page. The Customization tabs
display the same options that the Updates page displays. The Show Task
Changes button in the action menu re-directs you to the Update task changes
page. The number of days that are available in the task update history
section is set by the Project Server administrator.â€
 
G

Gary L. Chefetz [MVP]

Matric:

In the Project Server Database:

Table: MSP_WEB_ADMIN
Field: WADMIN_TRANS_HISTORY_DAYS
 