G
Grace
Hi!
Just wondering..
I need to change the display of gantt chart timescale in my project (remove
time scale breakdown of weekls in the bottom most tier and use weeks or
months) and same settings should apply on the Project Web Access (PWA) once I
publish it..
I tried saving and publishing the project with new settings on the timescale
but it did not reflect on the PWA.
How can I do it? Is it possible that the display will only apply in 1 project?
By the way, I am using MS Project Pro 2003 and MS Project Server 2003..
Kindly advise me.
Thanks!
Just wondering..
I need to change the display of gantt chart timescale in my project (remove
time scale breakdown of weekls in the bottom most tier and use weeks or
months) and same settings should apply on the Project Web Access (PWA) once I
publish it..
I tried saving and publishing the project with new settings on the timescale
but it did not reflect on the PWA.
How can I do it? Is it possible that the display will only apply in 1 project?
By the way, I am using MS Project Pro 2003 and MS Project Server 2003..
Kindly advise me.
Thanks!