How do I change the time scale display & reflect in PWA

G

Grace

Hi!

Just wondering..

I need to change the display of gantt chart timescale in my project (remove
time scale breakdown of weekls in the bottom most tier and use weeks or
months) and same settings should apply on the Project Web Access (PWA) once I
publish it..
I tried saving and publishing the project with new settings on the timescale
but it did not reflect on the PWA.


How can I do it? Is it possible that the display will only apply in 1 project?

By the way, I am using MS Project 2003..

Kindly advise me...

Thanks!
 
M

Mike Glen

Hi Grace,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top