RBFink
Most resources work 40 hours/week. However, I have one that works 32
hours/week. How do I set his work hours (Change working time - Calendar) so
the duration will be set correctly (fixed work tasks).
hours/week. How do I set his work hours (Change working time - Calendar) so
the duration will be set correctly (fixed work tasks).