how do I constrain a task to a day of the week

P

Paul Bartlett

Doing server migrations, I need to be able to say that one of the tasks
involved in the server migration can only happen on Sundays.

Can I constrain a task to only happen on a given day of the week eg Sunday
(not a specific date, a specific day)

Paul
 
J

JulieD

Hi Paul

if you're using Project 2000 or later you can create a calendar that has
Sunday only as a working day and assign that calendar to the task.

To create the calendar - tools / change working time - click on the new
button
To assign the calendar - double click on the task, go to the Advanced tab
and choose the calendar from the calendar drop down box.

Cheers
JulieD
 
P

Paul Bartlett

thankyou, that's perfcect :)

Paul

JulieD said:
Hi Paul

if you're using Project 2000 or later you can create a calendar that has
Sunday only as a working day and assign that calendar to the task.

To create the calendar - tools / change working time - click on the new
button
To assign the calendar - double click on the task, go to the Advanced tab
and choose the calendar from the calendar drop down box.

Cheers
JulieD
 