How do I convert Project 2003 durations (8h) to Excel 2003?

D

Dave

I am linking from Project Standard 2003 to Excel 2003. Durations and working
time are listed in Project as 8h Excel doesn't recognize this format.
 
J

JulieS

Hello Dave,

From excel do a find and replace to find "h" and replace with
nothing. Becareful when replacing days -- you want to maintain
consistency with your measurements. So if replacing 1 day -- I'd
convert to 8 hours in Project before exporting. In Project Tools >
Options, Schedule tab "Duration is entered in "hours". To convert
calculated durations (summary tasks) go to Tools > Macros > Macro
and run the Format_Duration macro.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top