Hello Dave,
From excel do a find and replace to find "h" and replace with
nothing. Becareful when replacing days -- you want to maintain
consistency with your measurements. So if replacing 1 day -- I'd
convert to 8 hours in Project before exporting. In Project Tools >
Options, Schedule tab "Duration is entered in "hours". To convert
calculated durations (summary tasks) go to Tools > Macros > Macro
and run the Format_Duration macro.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project