How do I create a predecessor that is linked to calendar days?

J

jt

I have a project where I am using working days as a 5 day week. Most of my
tasks with predecessors are linked based on a 5 day work week. Although I do
have a few tasks that are related in calendar days. The formula below works
for the 5 day work week, but not calendar days (when the weekend is included).

13FS+11d = finish to start plus 11 working days.

13FS+11??? = finish to start plus 11 calendar days???

please help, thanks
 
J

Jim Aksel

remember the term "elapsed" and you will have it. Project allows you to
enter elapsed time such as
13FS+11ed (11 elapsed days). This works with all time units. Some are a
little odd, such as emonths ...

Jim Aksel, MVP for Project
 