I am trying to create a specific work week/ work day calendar in project.
Example is that Friday could be workday 3 of a specific fiscal month and the
following Monday would be work day 4.
 
J

John

Michael said:
I am trying to create a specific work week/ work day calendar in project.
Example is that Friday could be workday 3 of a specific fiscal month and the
following Monday would be work day 4.

Michael,
You have posted in the developer newsgroup yet your question looks like
a general question on Project. Please see the MVP website at:
http://www.mvps.org/project/faqs.htm
and check out FAQ 24 - Project Newsgroups

I don't quite follow your example. There are many months wherein Friday
is the 3rd day of the month (e.g. Dec '04, Jun '05, etc.). And assuming
a normal 5 day workweek, the following Monday would be the 4th working
day. However you did mention "fiscal month". If by that you mean that
you need a calendar with non-standard months (e.g. 4-4-5 accounting
months), no version of Project is set up to handle that scenario
directly. It can be handled by using VBA and exporting the desired data
in accounting month form to another application (e.g. Excel), but
accounting month data cannot be set up directly in Project (at least not
easily or conveniently).

Hope this helps.
John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top