I have inherited a schedule that was created using a template for Project
Server (hence my posting here) but we are not using Project Server for this
project, just plain old project professional 2003.
The template and now schedule has a series of customised enterprise fields
in it that are not relevant for this project (and are confusing given I am
using local customised fields).
I have used organizer to delete the enterprise fields from the schedule but
each time I close and reopen the schedule they come back.
Are there any suggestions on how to get rid of them permanently.
Thanks
Server (hence my posting here) but we are not using Project Server for this
project, just plain old project professional 2003.
The template and now schedule has a series of customised enterprise fields
in it that are not relevant for this project (and are confusing given I am
using local customised fields).
I have used organizer to delete the enterprise fields from the schedule but
each time I close and reopen the schedule they come back.
Are there any suggestions on how to get rid of them permanently.