How do I display project status indicators in Project Web Access?

H

Harlow

The demo on Microsoft's website shows cool green, yellow, and red light
indicators in Project Web Access in the Project Center view for columns
"Project Schedule" and "Project Budget" but I cannot figure out how to set
those up. Anybody know how to do this?
 
D

Dale Howard [MVP]

Harlow --

You will need to create custom fields in the Enterprise Global file for each
of the columns you wish to see in PWA. When you customize each field, you
will need to create a formula to calculate progress according to either the
project schedule or the project budget, and then further customize the field
by displaying graphical indicators. Hope this helps.
 