A
Ayelet
I will be very happy to get an answer,
I have 1 resources which works every week on a different sum of tasks, for
example this week, he is working on 2 tasks 50% units each task, next week he
will keep working on this 2 task but will work parallel on 2 more new tasks
which means each task will get 25%, how can i set different units for the
same task, same resource but different weeks?
Thanks a lot Ayelet
I have 1 resources which works every week on a different sum of tasks, for
example this week, he is working on 2 tasks 50% units each task, next week he
will keep working on this 2 task but will work parallel on 2 more new tasks
which means each task will get 25%, how can i set different units for the
same task, same resource but different weeks?
Thanks a lot Ayelet