How do I enter Actual Costs?

M

Meg

I thought i could just insert the column and put it in there but it won't let
me. I went to the cost table and tried there and it won't let me do that
either.
 
D

Dominic

Meg,

If you have costs on a task as a result of entering a fixed cost figure or
arising from an assigned resource with a cost rate of more than $0.00
Microsoft Project will calculate actual cost for you as you update progress
on the task. By default costs are accrued on a pro-rata basis. So if you
have a task with a $50 fixed cost and a total cost of $100 due to there
being resource costs of $50 and the task is marked as being 50% complete the
actual and remaining cost values will be calculated as being $50.

Once a task is complete you can edit the actual cost figure at the task
level to be whatever you want.

--
Dominic Moss

Projectability - Helping People achieve more with Microsoft Project

www.projectability.co.uk
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top