D
DAR_Wpg_Canada
We have created a couple of different projects here in the office.
One started in Nov 2004, the other in Jan 2005.
Both projects started with the PMs putting people's time into their Projects
using Microsoft Project 2003.
Now, both projects are having time updated by the actual people.
However, the actual hours for each task have NOT been entered here. The
workers have 0.0s for their work in December and January. (Late January, they
started putting in their time using Project Server Web Access).
Now, each time the worker put in their time, they zero out the amounts put
in by their PMs for January.
How do we stop the PMs adjusted amounts from being blasted away?
I thought the worker's time could not affect the PMs adjusted amounts.
However, this is quite wrong.
We have discovered the Managed Periods option under Time Period Settings
underAdmin setting in Project Server 2003 Web Access. With this option
turned on, we can now limit what time period the workers can enter their time
in...however, it still allows their 0 time to blow away amounts entered by
the PMs.
I'm beginning to think that time entered by the workers MUST occurr before
any meaningful PM manipulation. If this is true, we do we do when someone
gets sick and hasn't entered their time yet? Or they go on vacation without
putting their time in?
One started in Nov 2004, the other in Jan 2005.
Both projects started with the PMs putting people's time into their Projects
using Microsoft Project 2003.
Now, both projects are having time updated by the actual people.
However, the actual hours for each task have NOT been entered here. The
workers have 0.0s for their work in December and January. (Late January, they
started putting in their time using Project Server Web Access).
Now, each time the worker put in their time, they zero out the amounts put
in by their PMs for January.
How do we stop the PMs adjusted amounts from being blasted away?
I thought the worker's time could not affect the PMs adjusted amounts.
However, this is quite wrong.
We have discovered the Managed Periods option under Time Period Settings
underAdmin setting in Project Server 2003 Web Access. With this option
turned on, we can now limit what time period the workers can enter their time
in...however, it still allows their 0 time to blow away amounts entered by
the PMs.
I'm beginning to think that time entered by the workers MUST occurr before
any meaningful PM manipulation. If this is true, we do we do when someone
gets sick and hasn't entered their time yet? Or they go on vacation without
putting their time in?