how do i filter to view only linked tasks?

R

Ron

i'm trying to filter a large project plan so we only view those tasks that
are linked and have dependencies. any idea how to do this? thank you. ron
 
G

Gérard Ducouret

Ron,

Project / Filter For... / More Filters... / Create
Field Name : Predecessors
Test : Not Equal to (or something like that : I don't have the English
version)
Value : left blank

Gérard Ducouret

Ron said:
i'm trying to filter a large project plan so we only view those tasks that
are linked and have dependencies. any idea how to do this? thank you.
ron
 
J

John

Ron said:
i'm trying to filter a large project plan so we only view those tasks that
are linked and have dependencies. any idea how to do this? thank you. ron

Ron,
The method I used (several years ago) was the following:
Predecessors is greater than 0
Or Successors is greater than 0

You probably want to turn off the option for Summary Lines.

Hope this helps.
John
Project MVP
 