I'm trying to find the best way to show late tasks in MSP 2002.

The Late/Slipping filter is not showwing what I want. I basically want to
be able to find out any task that should have been finished today and is not
at 100%. I can do it with filters but I can't figure out how to get this
info into MS Excel without the summary tasks.

So if you can help me set this up as a report I can run in MSP and then be
able to save it to MS Excel without it including the summary tasks. I'd be
eternally grateful.

Thanks
Tracey
 
T

Twinkletoes1971

Well I've worked out how to do this and I'm very proud of myself, even if I
do say so myself.
 