I'm trying to find the best way to show late tasks in MSP 2002.
The Late/Slipping filter is not showwing what I want. I basically want to
be able to find out any task that should have been finished today and is not
at 100%. I can do it with filters but I can't figure out how to get this
info into MS Excel without the summary tasks.
So if you can help me set this up as a report I can run in MSP and then be
able to save it to MS Excel without it including the summary tasks. I'd be
eternally grateful.
Thanks
Tracey
The Late/Slipping filter is not showwing what I want. I basically want to
be able to find out any task that should have been finished today and is not
at 100%. I can do it with filters but I can't figure out how to get this
info into MS Excel without the summary tasks.
So if you can help me set this up as a report I can run in MSP and then be
able to save it to MS Excel without it including the summary tasks. I'd be
eternally grateful.