S
Shawn Pollack
I don't understand how the sorting of external dependencies works.
I use a number of external depenencies in my workplans. (Predecessors and
successors linked to other workplans.) Project shows these tasks as a new
line (I call them "ghost tasks") in the originating file - you can see them,
but they are grayed out - you can't change them.
My question/issue has to do with the the placement of these tasks. Most of
the time, the "ghost tasks" are right next to the task that links to the
external dependency, but not always. When it works as I expect, the
predecessor ghost task is shown immediately above the linked task and the
sucessor ghost task is shown immediately below. But sometimes the ghost task
is several lines away from the linked task. I've not been able to figure out
any rule that is being followed for this apparent random placement of the
ghost task.
Is there something I can do so that the ghost task is always sorted right
next to (before for predecessors and after for successors) the originating
task? I regularly need to trace the predecessor/successor chain through my
files and it would be much easier to do if the ghost tasks were not
distibuted randomly.
I use a number of external depenencies in my workplans. (Predecessors and
successors linked to other workplans.) Project shows these tasks as a new
line (I call them "ghost tasks") in the originating file - you can see them,
but they are grayed out - you can't change them.
My question/issue has to do with the the placement of these tasks. Most of
the time, the "ghost tasks" are right next to the task that links to the
external dependency, but not always. When it works as I expect, the
predecessor ghost task is shown immediately above the linked task and the
sucessor ghost task is shown immediately below. But sometimes the ghost task
is several lines away from the linked task. I've not been able to figure out
any rule that is being followed for this apparent random placement of the
ghost task.
Is there something I can do so that the ghost task is always sorted right
next to (before for predecessors and after for successors) the originating
task? I regularly need to trace the predecessor/successor chain through my
files and it would be much easier to do if the ghost tasks were not
distibuted randomly.