B
Bill Zvonar
I've got 2 resources with different start dates working on a task... Project
insists on splitting the amount of work evenly between them, rather than
having them both work until the task is done.
How do I force both resources to work on the task until it's done?
More details...
I've defined a task (fixed work, work = 30wks).
Resource A is available in wk01.
Resource B is available in wk11.
If I assign Resource A, alone, to the task, it'll complete in wk30, as
expected.
If I assign Resource B, alone, to the task, it'll complete in wk40, as
expected.
Now, if I assign both Resource A & B to the task, Project insists on
dividing the Work between them equally. therefore Resource A stops working
on the task after wk15, even though after that, Resource B still works on
the task, alone, until wk25. Resource A doesn't have anything to do after
wk15 (i.e. he's at 0% after wk15).
I would expect that A would continue to work on the task until it's done,
which would mean they'd both work on it until wk20, and it'd be done then.
It seems to me that I'm missing, or misunderstanding, something
basic/obvious here. Any suggestions?
Some more context...
- Resource A & B both work 40h/wk while they're working... no contouring
- I get the same results if I define this as a 'fixed units / effort driven'
task
Thanks.
insists on splitting the amount of work evenly between them, rather than
having them both work until the task is done.
How do I force both resources to work on the task until it's done?
More details...
I've defined a task (fixed work, work = 30wks).
Resource A is available in wk01.
Resource B is available in wk11.
If I assign Resource A, alone, to the task, it'll complete in wk30, as
expected.
If I assign Resource B, alone, to the task, it'll complete in wk40, as
expected.
Now, if I assign both Resource A & B to the task, Project insists on
dividing the Work between them equally. therefore Resource A stops working
on the task after wk15, even though after that, Resource B still works on
the task, alone, until wk25. Resource A doesn't have anything to do after
wk15 (i.e. he's at 0% after wk15).
I would expect that A would continue to work on the task until it's done,
which would mean they'd both work on it until wk20, and it'd be done then.
It seems to me that I'm missing, or misunderstanding, something
basic/obvious here. Any suggestions?
Some more context...
- Resource A & B both work 40h/wk while they're working... no contouring
- I get the same results if I define this as a 'fixed units / effort driven'
task
Thanks.